Site Preparation
Customer must have the following ready at the time of installation:
- Plants work best when they are mounted on a concrete slab.
- Electric power must be ready at the site at the time of installation.
- Water must be ready at the site with a line to connect to the plant; maximum pressure 75 PSI.
Electric Power
Important Note: You need 1 1/2 times the current draw of the motor size for starting purposes.
Batch Plants
- 75 HP
- 480 Volts, 3 phase, 100 amps
- 120 Volts, single phase, 20 amps
Site Layout Drawing
Follow the site layout drawing carefully as provided in the installation documents for the specific plant model.
Set-up & Training
Set-up and training is included in the price of the plant. Customer must pay airfare and provide decent hotel and transportation while set-up and training is in process. Customer will provide all items listed in the Installation Agreement (attached). Customer pays electrician, scale calibration & hook-up, two men and equipment for assembly as needed.